Internal & External Works

Transforming Long Crendon During The Summer Closure

EQB Construction successfully delivered a comprehensive programme of refurbishment and external improvement works at Long Crendon School, Aylesbury, during the six-week summer closure period.

Working to a fixed programme ahead of the new academic year, the project required careful planning, coordination and sequencing to ensure all areas were completed, inspected and ready for pupils and staff returning to the school.

 

Internal Refurbishment Works

Internally, the works focused on improving and modernising a number of existing teaching spaces, creating brighter, more practical environments for staff and pupils.

The internal scope included:

  • Remodelling and refurbishment of existing classroom spaces
  • Removal and alteration of existing partitions
  • Installation of new glazed screens
  • Replacement windows
  • New internal doors and associated joinery
  • New flooring finishes
  • New suspended ceiling finishes
  • Mechanical and electrical alterations
  • Making good and associated finishing works
  • Full internal decoration package

 

The refurbishment required coordination across several trades within a compressed programme, with works sequenced carefully to ensure each area progressed efficiently through first fix, finishes and final completion.

External Improvement Works

 

The external element of the project included significant improvements to both the school car park and main playground areas.

Existing car park surfaces were removed and replaced with a new Bodpave system, providing an improved and more durable external environment. Associated works included:

 

  • Removal of existing car park surfaces
  • Installation of the new Bodpave surfacing system
  • New kerbs and edgings
  • New fencing
  • Construction of a new bin store
  • Installation of new storage sheds
  • Associated groundworks and finishing works

 

Within the main playground, EQB Construction also created a distinctive new enclosed play area incorporating curved blockwork walls and new fencing.

 

The wider playground was refreshed with new floor coatings and line markings, helping to create a safer, brighter and more engaging external space for pupils.

 

Delivering Within the Summer Closure

 

With all works required to be completed within the school’s six-week summer closure, programme management was a key consideration throughout the project.

 

Close coordination between the EQB Construction team, subcontractors, suppliers and the school ensured the various internal and external workstreams progressed concurrently while maintaining quality and keeping the programme on track.

 

The completed scheme has provided Long Crendon School with refreshed teaching spaces, upgraded external areas and improved facilities ready for the start of the new academic year.

 

Another successfully completed education project for EQB Construction, demonstrating our experience in delivering refurbishment, alteration and improvement works within challenging school holiday programmes.