John Hampden Grammar School

High Wycombe, HP11
Location:
Sector:
Highlights:
Building Extension, M&E Package

Delivering Phase 1 Within a Live School Environment

 

EQB Construction successfully completed Phase 1 works at John Hampden Grammar School, High Wycombe, delivering a substantial programme of construction and alteration works over a 21-week period.

The project involved extending and adapting the existing school facilities while maintaining operations within a live education environment. Careful planning, coordination and sequencing were therefore essential throughout to ensure works progressed safely and efficiently while minimising disruption to pupils, staff and the wider school community.

 

Enabling & Structural Works

The project commenced with enabling works and alterations to the existing school building, preparing the site for the main construction phase.

The initial scope included:

  • Enabling and preparatory works
  • Alterations to the existing school building
  • Groundworks and associated excavation
  • New drainage installations
  • Block-and-beam flooring
  • Structural steel frame installation
  • New brickwork and external envelope works

 

These works established the structure of the new extension and provided the foundation for the subsequent roofing, internal and M&E packages.

 

Building Envelope & Internal Works

 

Following completion of the main structural elements, the team progressed through the building envelope and internal fit-out programme.

 

Works included:

  • Roof structure and roof coverings
  • Installation of new windows and external doors
  • Internal partitions and associated finishes
  • Internal doors and joinery
  • Floor, wall and ceiling finishes
  • Decoration and final finishing works
  • Mechanical and electrical first fix
  • Mechanical and electrical second fix

 

Close coordination between the construction team and specialist subcontractors allowed multiple workstreams to progress efficiently within the overall programme.

 

Working Within a Live School

One of the key considerations throughout the project was delivering the works safely within a confined and operational school environment.

 

Maintaining clear segregation between construction activities and occupied areas was essential, alongside careful management of deliveries, access routes and site logistics.

 

Regular coordination ensured that:

  • Construction activities remained safely segregated from pupils and staff
  • Deliveries and vehicle movements were carefully managed
  • Noise and disruption were minimised wherever possible
  • Access routes remained safe and clearly controlled
  • Works were carefully programmed around the operational requirements of the school

 

This approach enabled the project to progress successfully while maintaining a safe environment for everyone on site.

 

Successful Completion & Continued Partnership

Phase 1 was successfully delivered within the planned 21-week construction programme, providing the school with improved facilities and additional space.

 

Following the successful completion of these works, EQB Construction was subsequently appointed to continue working at John Hampden Grammar School on a further project to provide additional classroom accommodation within an existing block.

 

The continued relationship is a strong example of the repeat business and long-term partnerships EQB Construction continues to develop across the education sector.

 

Another successfully completed education project demonstrating our experience in delivering extensions, alterations and refurbishment works within challenging live-school environments.